ClaimsPeople

Ørsted

Ørsted is a Danish energy company, formerly DONG Energy, that develops, builds and operates offshore wind farms and other renewable energy assets.

227 claims collected, 88 researched, 29 resolved. Report of 10 October 2026, method 0.1.0+7831dd9d.

Scores by kind of claim

Each kind of claim is scored on its own, out of 100: the share that held up, with the range it likely falls in. Fewer resolved claims give a wider range.

  • Factual claims

    Statements about the present or the past, checked against the record: did they hold up?

    84 73 93

    Medium confidence, 16 factual claims resolved. From 8 documents, 2014 to 2026; 8 documents sampled from 32 candidates found.

    Not scored: 12 unresolvable, 7 checkable only against their own records.

  • Predictions

    Statements about events outside the person's control, checked once they fell due: did they come true?

    46 27 65

    Low confidence, 7 predictions resolved. From 3 documents, 2014 to 2018; 8 documents sampled from 32 candidates found.

    Not scored: 5 unresolvable. 9 more fall due later.

    Does not yet allow for how likely each prediction was when made.

  • Promises

    Commitments to the person's or organisation's own future action, with something to deliver: was it delivered?

    60 40 79

    Low confidence, 6 promises resolved. From 4 documents, 2017 to 2021; 8 documents sampled from 32 candidates found.

    Not scored: 9 unresolvable, 16 not yet due, 1 checkable only against their own records.

All types combined: 70 (likely 61 to 78, medium confidence), from 29 claims: 16 factual claims, 7 predictions, 6 promises. It mixes kinds of claim in different proportions for different people, so compare people kind by kind.

Ørsted's claims

32 claims, sorted by newest said. Choose a claim to read it in full.
VerdictKindSaidClaimTopic
Not yet due Promise 13 Aug 2026 Ørsted will deliver an average ROCE of about 11% for 2026-2027 and above 13% for 2028-2030. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 13 Aug 2026 Ørsted's dividend policy for financial years 2026-2028 is expected to start at a modest level and increase annually. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 13 Aug 2026 Ørsted will deliver 2026 EBITDA above DKK 28 billion excluding new partnerships and cancellation fees. Promise · 13 Aug 2026 Their own work or organisation
Unresolvable Promise 13 Aug 2026 Ørsted maintains its gross investment guidance of DKK 50-55 billion. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 13 Aug 2026 Ørsted will announce the proposed dividend level in its Annual Report 2026. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 13 Aug 2026 Ørsted targets to reinstate dividend distributions for financial year 2026, with the first distribution in 2027. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 13 Aug 2026 Ørsted will reinstate a dividend payout to its shareholders as planned. Promise · 13 Aug 2026 Their own work or organisation
Not yet due Promise 6 May 2026 Ørsted maintains its gross investment guidance of DKK 50-55 billion. Promise · 6 May 2026 Their own work or organisation
Not yet due Promise 6 May 2026 Ørsted maintains its full-year 2026 EBITDA guidance of above DKK 28 billion excluding new partnerships and cancellation fees. Promise · 6 May 2026 Their own work or organisation
Not yet due Promise 7 Jun 2023 Ørsted has committed to reusing or recycling all wind turbine blades and solar panels from its global portfolio with immediate effect, and to commissioning only projects with a net-positive biodiversity impact from 2030. Promise · 7 Jun 2023 Their own work or organisation
Not yet due Promise 7 Jun 2023 Ørsted reaffirms its target of about 50 GW of renewable capacity in 2030. Promise · 7 Jun 2023 Their own work or organisation
Own records only Promise 7 Jun 2023 Ørsted will target an unlevered, fully loaded lifecycle IRR at a 150-300 basis point spread to WACC at the time of bid or FID, whichever comes first, while investing a majority of CAPEX in offshore. Promise · 7 Jun 2023 Their own work or organisation
Not yet due Promise 2 Jun 2021 Ørsted raised its ambition for renewable build-out from +30 GW announced at the 2018 Capital Markets Day to approx. 50 GW by 2030. Promise · 2 Jun 2021 Their own work or organisation
Not yet due Promise 2 Jun 2021 Ørsted sets the ambition that no later than 2030 all new projects it commissions will have a net-positive biodiversity impact. Promise · 2 Jun 2021 Their own work or organisation
Not yet due Promise 2 Jun 2021 Ørsted plans to invest approx. DKK 350 billion in green energy from 2020 to 2027, raising average yearly investments by approx. 50% since the last Capital Markets Day. Promise · 2 Jun 2021 Their own work or organisation
Not yet due Promise 2 Jun 2021 Ørsted sets the ambition to reach approx. 50 GW of installed renewable capacity by 2030. Promise · 2 Jun 2021 Their own work or organisation
Not yet due Promise 2 Jun 2021 Ørsted sets the ambition of reaching approx. 50 GW of installed renewable energy capacity by 2030, more than quadrupling its installed capacity over the next decade. Promise · 2 Jun 2021 Their own work or organisation
Unresolvable Promise 2 Jun 2021 Ørsted commits to reuse, recycle or recover 100% of blades from repowering or end-of-design-life decommissioning of its onshore and offshore wind farms. Promise · 2 Jun 2021 Their own work or organisation
Mostly true Promise 2 Jun 2021 Ørsted announced on 2 June 2021, with immediate effect, a ban on landfilling of wind turbine blades. Promise · 2 Jun 2021 Their own work or organisation
Unresolvable Promise 9 Sep 2020 Henrik Poulsen will serve as special advisor to Mads Nipper until 31 January 2021 to support a smooth transition. Promise · 9 Sep 2020 Their own work or organisation
Mostly true Promise 9 Sep 2020 Henrik Poulsen will remain in office as Ørsted CEO until 31 December 2020. Promise · 9 Sep 2020 Their own work or organisation
Unresolvable Promise 9 Sep 2020 In 2021 the CEO's total target remuneration at Ørsted will be approximately DKK 20 million. Promise · 9 Sep 2020 Their own work or organisation
Mostly true Promise 9 Sep 2020 Mads Nipper will take office as Ørsted CEO on 1 January 2021. Promise · 9 Sep 2020 Their own work or organisation
Unresolvable Promise Feb 2018 Ørsted targets at least 95% of its heat and power generation to be green in 2023. Promise · Feb 2018 Their own work or organisation
Mostly true Promise Feb 2018 Ørsted's future guidance will only include the effect from existing offshore wind partnership agreements. Promise · Feb 2018 Their own work or organisation
Resolved false Promise 2017 DONG Energy will stop using coal altogether at its power plants from 2023. Promise · 2017 Their own work or organisation
Delivered on time Promise 2017 DONG Energy's target is that 60% of the biomass it buys during 2017 will be certified as sustainable. Promise · 2017 Their own work or organisation
Not yet due Promise 2017 DONG Energy aims to phase out coal completely from its power and heat generation by 2023. Promise · 2017 Their own work or organisation
Unresolvable Promise 2017 DONG Energy targets an average ROCE up to 2023 of 12-14% for the Group, 13-15% for Wind Power and 9-11% for Distribution & Customer Solutions. Promise · 2017 Their own work or organisation
Unresolvable Promise 2017 DONG Energy maintains its target of a lost-time injury frequency (LTIF) of 1.5 by 2020. Promise · 2017 Their own work or organisation
Unresolvable Promise 2017 DONG Energy's target is that 100% of the biomass it buys will be certified as sustainable by 2020. Promise · 2017 Their own work or organisation
Unresolvable Promise Feb 2014 DONG Energy's objective is for FFO to be around 30% of adjusted net debt from 2015 onwards. Promise · Feb 2014 Their own work or organisation
Back to the list

Ørsted

Open its page

Promise Their own work or organisation

“We remain on track to deliver on an average ROCE of ~11 % for 2026–2027 and above 13 % for 2028–2030.”

Ørsted 13 August 2026 Ørsted continues its strategic progress, delivers solid operational performance, and is on track to deliver on its 2026 financial guidance (Ørsted)

Ørsted will deliver an average ROCE of about 11% for 2026-2027 and above 13% for 2028-2030.

Not yet due The date it refers to has not come.

Reasoning

deadline 2030 is after 2026-10-10

Cite this claim

Ørsted, “Ørsted will deliver an average ROCE of about 11% for 2026-2027 and above 13% for 2028-2030.” (said 13 August 2026). Verdict: not yet due. Reliability API, claim c_2348297414f3, method 0.1.0+7831dd9d. https://epistacklabs.com/claims/c_2348297414f3

Claims without a verdict