The projects building out AI infrastructure with OCI, OpenAI and SoftBank are contracted and being worked on.
Mostly true True in substance, wrong in a detail.
Factual: Statements about the present or the past, checked against the record: did they hold up?
The second judge would not resolve this claim; the verdict shown is the first judge's.
Said for an organisation they lead or work for; it counts on both records.
What would count as true or false
Judged as of 2025-09-26. True: signed contracts or definitive agreements (not just letters of intent or MOUs) existed for the AI-infrastructure projects involving OCI/Oracle, OpenAI and SoftBank (for example Stargate sites and the Oracle–OpenAI compute agreement), and work such as site development or construction was underway. Mostly true: the main projects were contracted and underway, but a minor component was still only at a non-binding stage. Mixed: roughly half of the referenced projects were contracted and underway, while others were only announced or under negotiation. Mostly false: the projects were mainly announced, planned or at the LOI stage, with only small parts contracted. False: as of that date the projects were not contracted and no work had begun.
Set before the research began.
Evidence (11)
-
E1 List of AI compute deals | AI Wiki AI Wiki · 15 October 2026
“Oracle disclosed on June 30, 2025 that it had signed a cloud contract, with a customer it did not name, expected to bring in more than $30 billion a year from its fiscal 2028”
-
E2 OpenAI's $500 billion 'Stargate' project faces setbacks - Quartz Quartz · 22 July 2025
“According to unnamed sources, the companies have yet to cement any deals for a data center and they haven't decided on any locations.”
-
E3 Stargate Project | AI Wiki AI Wiki · 8 May 2026
“the first campus, in Abilene, had been under construction since June 2024”
-
E4 Stargate Project | AI Wiki AI Wiki · 8 May 2026
“Oracle began delivering the first Nvidia GB200 racks in June 2025, and OpenAI began running early training and inference workloads soon afterward”
-
E5 List of AI compute deals | AI Wiki AI Wiki · 15 October 2026
“Oracle disclosed on June 30, 2025 that it had signed a cloud contract, with a customer it did not name, expected to bring in more than $30 billion a year from its fiscal 2028”
-
E6 List of AI compute deals | AI Wiki AI Wiki · 15 October 2026
“Contract: OpenAI's figure for its 4.5 GW Oracle partnership over five years; The Wall Street Journal had reported purchases from 2027, a start neither company confirmed, and Oracle has not stated the value”
-
E7 Stargate Project | AI Wiki AI Wiki · 8 May 2026
“that Stargate, having completed no data center deals, was aiming for a smaller data center in Ohio by the end of 2025”
-
E8 Oracle Fact Sheet: Stargate Data Centers Oracle (fact sheet hosted at arrington.house.gov) · 23 September 2025
“Construction on the campus has already begun, with the first building scheduled for delivery in the second half of 2026.”
-
E9 Stargate Advances with 4.5 GW Partnership with Oracle OpenAI · 22 July 2025
“Oracle and OpenAI have entered an agreement to develop 4.5 gigawatts of additional Stargate data center capacity in the U.S.”
-
E10 OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites | SoftBank Group Corp. SoftBank Group Corp. · 24 September 2025
“One site is located in Lordstown, Ohio, where SoftBank has broken ground on an advanced data center design which is on track to be operational next year.”
-
E11 Oracle Fact Sheet: Stargate Data Centers Oracle (fact sheet hosted at arrington.house.gov) · 23 September 2025
“County commissioners just approved an industrial revenue bond to move the project forward.”
Reasoning
OpenAI announced in July 2025 that it and Oracle had entered an agreement for 4.5 GW of Stargate capacity (E10). Abilene had been under construction since June 2024, with GB200 racks delivered from June 2025 (E4, E5). By late September, Oracle reported construction under way and SoftBank reported breaking ground at Lordstown (E9, E11). Some components were at an early stage; for one project, county commissioners had just approved an industrial revenue bond to move it forward (E12). July reports of no completed data center deals (E2, E8) came before the September announcements.
Cite this claim
Jensen Huang, “The projects building out AI infrastructure with OCI, OpenAI and SoftBank are contracted and being worked on.” (said 26 September 2025). Verdict: mostly true. Reliability API, claim c_31680699311e, method 0.1.0+03d23c0e, dataset release v1.1.2. https://epistacklabs.com/claims/c_31680699311e
This claim is in dataset release v1.1.2, with the same verdict.
Reply to this claim
More factual claims by Jensen Huang
-
Mixed
“the reason why NVIDIA’s growth is accelerating is because people are starting to realize that we’re the safest architecture to invest in.”
-
Mostly true
“Trillions of dollars in investment.”
Current investment in AI is on the order of trillions of dollars.
-
Mostly true
“Today, it’s dollars per million tokens.”
AI intelligence is now monetized and priced in dollars per million tokens.
-
Mixed
“Each one of these at one gigawatt level started at $20, $30 billion dollars.”
-
Mostly true
“Now CoreWeave is worth $50, $60, $70 billion dollars and growing incredibly fast.”
CoreWeave is now worth $50, $60 or $70 billion and is growing very fast.